Princeton Farms Sewer Rehabilitation Project Status Report February 9, 2024
Princeton Farms Sewer Rehabilitation Project Status Report
The following list identifies progress and relative action items that remain for completion of the Princeton Farms Sewer Rehabilitation Project:
Contractor completed pre-lining efforts by cleaning and televising sanitary sewer lines
Manhole frame and covers installed Contractor has completed the following lining efforts to date:
- Darrow Drive: PF6 to MH-32 (Completed)
- Westcott Blvd: PF14 to PF11 (Completed)
- Weldon Way: PF27 to PF 26 and PF30 to PF29 (Completed)
- Pennington Rocky Hill Road: PF46 to PF43 (Completed)
- Drummond Drive: PF41 to PF40 (Completed)
- Caroline Drive: MH19 to MH20 (Completed)
- Morris Drive: MH 8 to MH9 (Completed)
Contractor has completed all lateral lining efforts with the exception of 105 Darrow Drive
Contractor has completed the following manhole rehabilitation efforts:
February 2024 –Grouting and Manhole Rehabilitation
Early March 2024 – Anticipated Construction Completion.