Milling and paving work scheduled for Bear Tavern Road

 On or about Monday, June 27, 2016, Mercer County D.O.T. will commence milling resurfacing work on Bear Tavern Road (CR 579) from Maddock Road to Church Road in Hopewell Township.

 Work will be performed from 9:00 a.m. to 3:00 p.m., Monday through Friday.

 Mercer County proposes to complete the milling and resurfacing of Bear Tavern Road as follows:

 Phase One: Half width construction from Maddock Road to Washington Crossing Road. Traffic would be maintained in the northbound direction. Southbound traffic would be detoured with motorists directed to use Washington Crossing Road to Jacobs Creek Road.

 Phase Two: Half width construction from Washington Crossing Road to Church Road. Again, traffic would be maintained in the northbound direction. Southbound traffic would be detoured with motorists directed to use Pennington-Harbourton Road, Scotch Road and Washington Crossing Road.

 Full, unrestricted access will be permitted during non-working hours.

 Mercer County anticipates this work will take approximately fifteen (15) working days, weather permitting.

 

Road Construction Notice

The Province Line Road CSX Railroad Crossing will be undergoing reconstruction beginning today, Monday, June 20th and will remain closed for approximately 1 week.

The crossing will be impassable to all traffic during this period.

 Detour: County Route 518 to Hopewell Amwell Road.

  

Road Construction Notice

Beginning on or about Monday, May 2, 2016, Mercer County DOT will be rehabilitating the stone arch of the Wargo Road Bridge located approximately ½ mile north of Titusmill Road.

This will require a full closure of Wargo Road on a 24/7 basis.

The work is anticipated to last approximately 90 days.

During construction, a detour will be posted directing motorists to use Pennington-Rocky Hill Road, Darrow Drive, Westcott Boulevard and Bradford Lane.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 


 Please continue check this advisory banner for further updates.    Refresh/reload the page periodically to ensure you are seeing the latest information.

   Home
Contact Us
 
 

Marshalls Corner Pennytown Redevelopment

Submit Comments and Questions about this project.
Name *
Address *
City *
State *
Email *
Confirm Email *
Subject *
Comments *
Enter the anti-spam code shown in the box:

(The documents below are PDF documents and you will need
the free Adobe reader to view them)

Planning Reports and Redevelopment Illustrations
  Pennytown Task Force Meeting - March 19, 2014
  Meeting with Hopewell and Pennington Borough  - 3/28/13
  Pennytown Alternates - 3/28/13
  Marshall's Corner Pennytown - Slide Show - 3/21/13
  Marshall's Corner Pennytown Redevelopment Report - 3/14/13
  Marshall's Corner/Pennytown Project Fiscial Impact Report - 3/8/13
  Task Force Consensus Documents - Updated 2/28/13
  Task Force Consensus Documents - (2/28/2013)
  Marshall's Corner Pennytown Costs - (2/7/2013)
  Marshall's Corner Pennytown Redevelopment Planner's Report - (2/7/2013)
  Marshalls Corner - Pennytown Redevelopment Presentation - (4-19-12)
  Marshall's Corner/Pennytown Task Force -Township Committee Meeting, (5-23-2011)
  Slide show from the last MC-Pennytown Task Force meeting - (3-17-11)
  Capitaization Rate Information - (3-17-11)  
  Pennytown Planners Final Report (8-17-09, 13MB)

Wastewater Evaluations
  MCP Redevelopment Wastewater Presentation - (3/14/13)
  Report - May 1, 2009 - Pennytown Village Wastewater System Evaluation (2/20/2013)
  Meeting Presentation by Natural Systems Utilities
  Pennytown Kooltronic Sites Wastewater Treatment and Disposal Assessment - (2/7/2013)

Water Evaluations
  Hydrogeologic Evaluation of the Pennytown-Kooltronics Re-Development Site in Hopewell Township, Mercer County, New Jersey - 01/17/2013
  Letter from M2 Associates - Nov. 3, 2008 - Proposed Acquisition of Pennytown Site, Block 33 Lot 1 (2/20/2013)
  Letter from M2 Associates - May 21, 2009 - Aquifer Testing Results and Hydrogeologic Evaluation of the Pennytown Site, Block 33 Lot 1, (2/20/2013)
  Meeting Presentation by M2 Associates
  Hydrogeologic Evaluation of the Pennytown-Kooltronics Re-Development Site - (2/7/2013)
  Hydrologic Technical Report - (1/11/2013)

Traffic Evaluations
  Rt. 31 Design Study - 3/28/13
  Traffic Presentation - 3/28/13
  Analysis of Traffic Impact - Final Report - Revised 03/20/2013
  Orth-Rodgers & Associates - Marshall's Corner / Pennytown Redevelopment Area

Meeting Audio / Video Links
Video Library (select Categories and then Pennytown Redevelopment)
Guest Column
-
September 23, 2010
   
 

 

 
TextMenu | Privacy Statement | Register for E-mail Notifications | Contact Us
201 Washington Crossing - Pennington Road  •  Titusville, NJ 08560  •  (609) 737-0605